@startgantt
|
|
printscale daily zoom 4
|
|
|
|
!define LIGHTRED #fd26008f
|
|
|
|
[Sprint 2026-3] requires 14 days
|
|
Project starts 2026-02-09
|
|
-- ✓ API-9489 --
|
|
[Sprint 2026-3] starts 2026-02-09
|
|
[Формирование драфта спеки] starts 2026-02-09
|
|
[Формирование драфта спеки] is colored in LightGreen
|
|
[Формирование драфта спеки] requires 3 days
|
|
-- ▶ API-9576 --
|
|
[Реализация Фазы 1] starts 2026-02-12
|
|
[Реализация Фазы 1] is colored in lightgreen
|
|
[Реализация Фазы 1] requires 2 days
|
|
|
|
' Подсветка выходных
|
|
2026-02-14 to 2026-02-15 are colored LightBlue
|
|
2026-02-21 to 2026-02-22 are colored LightBlue
|
|
|
|
legend left
|
|
Legend:
|
|
|= Icon |= Task progress |
|
|
| ✓| Completed |
|
|
| ▶| In Progress |
|
|
| ■| Not started |
|
|
|
|
|= Color |= Subtask status |
|
|
|<#lightgrey> | Not started |
|
|
|<#cyan> | In progress |
|
|
|<#lightgreen>| Completed |
|
|
|<LIGHTRED> | Declined |
|
|
end legend |